This is the last week for the build for this year. Unfortunately we do not have handover before Christmas as we'd hoped for. Nevertheless the build has been so far has been consistent to what the Site Supervisor had planned.
The progress so far are the electricals and bits and pieces such as sink, tap, etc are all done. What's left to do for next year are the shower screens and flooring. We're going to have Timbernate Brushbox flooring for most of ground floor and Redbook Green Sustainable Carpet for first floor.
Then last but not least the cleaning of the house and PCI. Yes PCI was estimated to be early Feb because SS will be back after the 20 Jan. Not sure if there will be any work between end of this week until end of Jan. Hope so.
For anyone reading this, have a Merry Christmas and a wonderful New Year 2014. Be safe.