Wednesday, November 13, 2013

Week 14: more Gyprocking and stairs

Mon 11 Nov 2013 - Sun 17 Nov 2013

More gyprocking this week. Cornices  done on some area, lower bricks now cleaned, electrician already back to pull the cables out from behind the gyprocks.






Plan for next week are stairs, carpenter to install doors and then we're in lockup stage, then also kitchen cabinet and waterproofing for next week too. Wow lots of happening. 

Friday:
Wow. The stairs has been delivered and installed today








 

Sunday, November 3, 2013

Week 13: Wall Insulation and Gyprock

Mon 4 Nov 2013 - Sun 10 Nov 2013

Monday: Wall Insulation to start and finish today. Tomorrow tuesday is the day gyprocks to be delivered. Not sure if gyprock-ing can start tomorrow. 

Thanks to one lovely homeone forum user 'dotgif' and our friend who live nearby for sending us these photos. 

Cladding to front of house and eaves above cladding were installed today. 




Blueboard texture based sheeting to the rear of the house was also installed today. 

Wall insulations appear to be installed throughout. 






Tuesday: Gyprocks are delivered. 


Friday and Saturday: they work on Saturday to finish off the gyprocking

Entry

Foyer

Home theatre

View to living area from dining area










Sunday, October 27, 2013

Week 12: Electrical

Mon 28 Oct 2013 - Sun 3 Nov 2013

Monday: Today is the day the electrician start cabling


NBN



Where all my Data Cat6 cables terminate

Extra noggins for TV


Thursday: Howard Ryan Inspection is scheduled for this day
UPDATE: the inspection report was great. No major issues and very few minor issues addressed by monday.

Saturday: Added my own speaker cables all the way from Home Theatre to the living area. Unfortunately I only got 3 x 30M speaker cables and it was too short, so I had to cut corners by pre-wiring speaker cables for Dining area and Alfresco from the TV point in the Living room.

Monday, October 21, 2013

Week 11: Lower roof

Mon 21 Oct 2013 - Sun 27 Oct 2013

Monday: one of fellow user (dotgif) from homeone forum was kindly enough to tell us that lower roofing is done and sent us some pictures below. 




Wednesday: looks like a sliding door frame delivery and .. Hmm .. Looks like a cladding material. 





Monday, October 14, 2013

Week 10: Eaves Painted, Scaffolding Down, AC and more

Mon 14 Oct 2013 - Sun 20 Oct 2013

Monday: Eaves painted

Friday: scaffolding down, bricks cleaned first floor wall up, stairs wall moroka half done. 





Saturday: ducted AC installed, except tr outdoor unit. 









Electrical box is installed too


Lower roof fascia done

Hot water box is done










Thursday, October 10, 2013

Week 9: Bricks cleaned

Mon 7 Oct - Sun 13 Oct 2013

Bricks to be cleaned this week. 

Thursday:
Bricks cleaned, fascia done, eaves not painted yet.



Sunday:

Bricks cleaned up close





First floor waste plumbing

Eaves not yet painted








Sunday, September 29, 2013

Week 8: Final Bricking

Mon: 30 Sep 2013 - Sun 6 Oct 2013

Monday: SS informed me last friday that this week plan will be to finish the bricking. Then possibly end of this week and next week to start brick cleaning and installing downpipes while the scaffolding still exists.

Wednesday:


Thursday: